BASE Read-only job info
Job #25267 Jenks ESC Remodel Customer: Jenks Public Schools PM Foreman Trade: Plumbing
Last edited by PM 2 minutes ago
Margin $67,655 · 15.11% / 13.12% / $16.94/hr · 33.88%
15.11% to Cost 13.12% to Sell $16.94/hr to Man-Hr 33.88% to Labor

Cost Codes

Description · Qty/Rate/Cost · Total · firm-quote toggle · Notes

Description Qty/Rate/Cost Total ✓ Firm Quote Notes
▾ Plumbing Equipment 5 lines · $94,790
21-C Contingency $25,221 + 1% $25,473 Remainder target line
21-C Boone & Boone $0 $0 Supplier placeholder
21-C Tulsa Winnelson $0 $0 Supplier placeholder
21-C Ferguson $0 $0 Supplier placeholder
21-C Hajoca $68,631 + 1% $69,317 📎 Quote attached
▾ Plumbing Pipe & Material 3 lines · $94,799
01 Underground $8,088 + 1% $8,169 Material phase
02 Top Out $70,585 + 1% $71,291 Material phase
03 Fixture Set & Trim Out $15,187 + 1% $15,339 Material phase
▾ Plumbing Labor Rate $50 · $199,700
Misc80 hrs @ $50$4,000Labor allowance
Underground1,571 hrs @ $50$78,550Primary rough-in labor
Top Out1,377 hrs @ $50$68,850Overhead phase
Fixture344 hrs @ $50$17,200Set and trim
Utilities0 hrs @ $50$0Template line
Gas Piping382 hrs @ $50$19,100Gas phase
Insulation0 hrs @ $50$0Template line
Plumb Temp200 hrs @ $50$10,000Temporary plumbing
Punch List40 hrs @ $50$2,000Closeout
▾ Subcontract Costs 1 used line · $23,905
Environmental Action Lump sum $23,905 Subcontractor scope
6 zero-value subcontract lines collapsed by default
▾ Job Expenses 3 lines · $34,618
Equipment RentalsLump sum$26,000Estimated rentals
City/State PermitsLump sum$1,000Permitting allowance
Bond PremiumLump sum$7,618Bond quote