HVAC

24174 Phillips Theological Seminary

· Nabholz Client Service · Prog Billing
Contract
$606,000
Billed
$606,000 (100%)
Spent
$481,200
Effective margin
20.6%
Net margin $
+$124,800

Monthly Project Revenue vs Expenses

Field Roster · this/last week

4 / 5
guys this wk · last wk
  • Smith, Daniel38h
  • Johnson, Marcus40h
  • Reed, Caleb36h
  • Vega, Luis22h

Bills

14
since last pay app · $48,200

Pay Apps

8
last issued: 2026-04-21

Labor Forecaster

Last edited 2026-04-23
Open forecast →

CTC

2 outstanding adjustments
Open CTC →

Contract Folder

📁 03 - Contract

Change Orders 3

Daily Reports · field running summary

📁 Open Daily Reports folder
Most recent first · scroll for history · answers from BusyBusy field forms · PDFs available in folder if needed
2026-05-04 · Mon Smith, Daniel · 4 guys on site · 8 hrs
Work performed: Set first-floor RTU curbs and hung supply duct mains on the east wing through grid line E-7. Hooked up condensate drains.
Manpower: 4 (D. Smith, M. Johnson, C. Reed, L. Vega)
Issues / delays: Lift came in 90 min late from Sunbelt — lost ~1.5 hrs on east-wing hangers.
Safety: No incidents. Pre-task hazard analysis filed.
Tomorrow: Continue duct mains west wing, start VAV box rough-in.
2026-05-03 · Sun — · weekend · no crew
No report filed.
2026-05-02 · Sat Smith, Daniel · 2 guys on site · 6 hrs
Work performed: Saturday catch-up. Punched out two leak-test failures on first-floor mains. Cleaned penthouse and staged Monday's curb hardware.
Manpower: 2 (D. Smith, C. Reed)
Issues / delays: None.
Safety: No incidents.
Tomorrow: Off.
2026-05-01 · Fri Johnson, Marcus · 5 guys on site · 8.5 hrs click to expand
Work performed: Continued main duct runs east wing. RTU-3 set on curb, prepped for crane pick on RTU-4 next week.
Manpower: 5 (D. Smith, M. Johnson, C. Reed, L. Vega, J. Hardy)
Issues / delays: 30 min lost waiting on Nabholz electrician for disco circuit.
Safety: No incidents. Tied off on penthouse work.
Tomorrow: Saturday catch-up — 2 guys.
2026-04-30 · Thu Smith, Daniel · 4 guys on site · 8 hrs click to expand
… (full Q&A loads on expand)

Photos 12 this week

+6
📁 Open Photos folder →

Project-to-Date Docs

  • 📄 Lien waiver — May 21
  • 📄 COI — current
  • 📄 W-9 — on file
  • 📄 RFI #014 — open
  • 📄 RFI #013 — closed
  • 📄 Submittal log — current

Mockup for review — four boxes redesigned: Box 1 chart (stacked Subs/Materials/Labor + revenue line + Profit segment when revenue exceeds expense), Box 4 Pay Apps (PDF hyperlinks via modal), Bills + Change Orders mirror that pattern, Box 10 Daily Reports rebuilt (2x4 footprint, BusyBusy answers in a date-grouped accordion, single folder-jump button replaces per-row PDF links), Box 11 Photos lightbox (click any thumbnail; arrow keys or chevrons to navigate).