Mockup · Projects view · Option A: tabbed page

All project information consolidated under tabs

Sticky header carries the always-visible numbers. Tabs swap the body. Compare with Option C (hub & spoke) at projects_view_option_c_hub.html.

← All projects

Tulsa Community College — SE Campus Restrooms

Key Construction · Owner: Tulsa Community College · Tulsa, OK · contract signed 2026-01-08

In Progress ⚠ 1 actual overrun
Contract
$1,250,000
Billed
$812,000
65% of contract
Spent
$740,000
Effective margin
$197,500
15.8%
Net margin impact
+$10,000
2 CTCs · margin gain
Overview
Budget 1 over
Forecast 14d
Expenses 🚧
Invoices 🚧
Reports
Documents 🚧
Activity 3

Tab: Overview

Default landing — health snapshot in one screen.
Cost-to-complete
$332,500
remaining vs effective
Forecast — this month
$78,300
labor + materials, April
Days to next pay app
7
cycle ends May 20
Latest CTC filed
+$15,000 margin gain
Underground · 3d ago

Recent activity

View all →
  • ✦ CTC
    Margin gain +$15,000 from Plumbing — Underground
    Josh M. · 2026-04-22 · "Underground came in clean — no rock"
  • ⚠ CTC
    Margin draw −$5,000 for Plumbing — Top-out overrun
    Josh M. · 2026-04-22 · "Tile spec required additional labor"
  • 📅 Close-out
    March 2026 closed · profit impact +$2,400
    Josh M. · 2026-04-15
  • 🔄 Sync
    Pulled CO #3 from QB · +$8,000 to Plumbing — Top-out
    automatic · 2026-04-10
  • 📝 Status
    Status changed: AwardIn Progress
    Josh M. · 2026-03-12

Needs attention

3 items
  • 🚨
    Plumbing — Trim is over by $4,200
    Spent $82,200 vs effective $78,000. Close-out blocked until a CTC is filed.
  • CTC review is 14 days old
    3 cost codes haven't been reviewed yet (HVAC — Equipment, Test & Balance, Insulation).
  • 📭
    1 closeout override needs CTC formalization
    HVAC — Equipment, +$8,400 acknowledged 30 days ago without a CTC.

About this project

From QuickBooks · synced 2h ago
GC PM
Mike Rose
mrose@keyconst.com · (918) 555-0142
Send invoices to
ap@keyconst.com
CC: mrose@keyconst.com
Project address
10300 E 81st St
Tulsa, OK 74133
Owner
Tulsa Community College
Public · prevailing wage
Contract date
2026-01-08
scheduled completion 2026-09-30
Pay app cycle
20-to-20 monthly
retainage 5% on each draw

Tab: Budget

The meat of the page — original + COs + CTCs layered.
Cost code Original + CO + CTC Effective Spent Remaining % used
Plumbing — Labor & Materials $320,000 +$12,000 $332,000 $215,000 $117,000 65%
Plumbing — Underground $95,000 −$30,000 $65,000 $58,000 $7,000 89%
Plumbing — Top-out $145,000 +$8,000 +$20,000 $173,000 $95,000 $78,000 55%
Plumbing — Trim ⚠ $78,000 $78,000 $82,200 −$4,200 105%
HVAC — Labor & Materials $285,000 +$15,000 $300,000 $198,000 $102,000 66%
HVAC — Equipment $92,000 $92,000 $92,000 $0 100%
Bonds & Permits $8,500 $8,500 $7,200 $1,300 85%
Insulation (sub) $28,000 $28,000 $0 $28,000 0%
Test & Balance (sub) $11,000 $11,000 $0 $11,000 0%
Margin / Profit $187,500 +$10,000 $197,500
Project total $1,250,000 +$35,000 $0 $1,285,000 $747,400 $340,100 58%
Effective = Original + COs + CTCs. Margin row = revenue side; doesn't get a "Spent" or "Remaining."

Tab: Forecast

Embeds the existing /labor-forecast/project/:listId editor — same UX, same close-out wizard.
Showing 6 months · click any cell to set %. Full editor at /labor-forecast/project/QB-list-id.
Cost code Apr 2026 May Jun Jul Aug Sep
Plumbing — L&M
25%
$29K
19%
$22K
19%
$22K
19%
$22K
19%
$22K
Plumbing — Top-out
30%
$23K
30%
$23K
20%
$16K
20%
$16K
HVAC — L&M
17%
$17K
17%
$17K
17%
$17K
17%
$17K
17%
$17K
17%
$17K
Insulation (sub)
100%
$28K
Hard (locked) Auto (re-proportions live) Empty (click to include)

Tab: Invoices · Under construction

What a greyed/disabled tab body looks like.
🚧

Pay app cycle & invoice management coming next

This tab will pull together every invoice issued, the active pay app, retainage, and AR aging — for this project specifically.

Will live here
· Issued invoices (with attached pay-app PDFs)
· Pay app schedule (20-to-20 cycle, retainage 5%)
· Retainage tracking + release stage
· AR aging for this GC
· "Compose pay app backup" — bulk PDF download

Target: Q3 2026 · gated on Monthly Billing Helper feature. See roadmap.

All four sample tab bodies rendered above. Other tabs (Reports, Documents, Activity) follow the same patterns. Generated 2026-04-25.